• Back to news

Port City construction progress (10.08.21)

18.08.2021
Port City construction progress (10.08.21) Port City construction progress (10.08.21)

Fresh report from the Port City construction site! We have good news - all three blocks are completely cast!

1 block:

  • monolith — 100%;
  • masonry 100%;
  • ventilation — 100%, (ventilation equipment at the final stage);
  • sewerage, water supply — 100% (risers were installed, work was done on the inter-apartment wiring, meters were installed);
  • fire safety cables have been laid, fire cabinets are being formed;
  • roofing device — 100%;
  • installation of aluminum subsystems, balcony railings — 95%; facade works are in full swing, installation with double-glazed windows, ceramics, sandwich panels is 30% completed.

2 block:

  • monolith — 100%;
  • masonry — 100%;
  • ventilation 95%, ventilation equipment is being installed);
  • sewerage water supply — 95% (installed risers, intra-apartment wiring, installation of meters);
  • roofing device: the screed is 100% completed, the first layer of waterproofing was applied;
  • Facade: 70% of aluminum substructures installed, 15% of sandwich panels.

3 block:

  • monolith — 100%;
  • masonry — 65%;
  • ventilation — 70%;
  • sewerage, water supply — installation of risers has begun, readiness - 30%;

Also, at the moment, work is being actively carried out on the installation of engineering networks of the parking lot.

Оберiть мову: