Port City construction progress

11.10.2021
Port City construction progress Port City construction progress

We invite you to find out the dynamics of the construction of the Port City apart-complex.

1 block:

  • Monolith — 100%;
  • masonry — 100%;
  • ventilation — 100%, (ventilation equipment at the final stage)
  • sewerage, water supply — 100% (risers installed, intra-apartment wiring completed, meters installed);
  • fire safety cables have been laid, fire cabinets are being formed;
  • roofing device — 100%;
  • work is being done on the construction of transformer substations, installation of equipment, arrangement of premises;
  • installation of aluminum subsystems, balcony railings — 95%;
  • Facade works are in full swing, installation with double-glazed windows, ceramics, sandwich panels — completed by 40%;
  • facade lighting (power cable lines laid, the first lamps installed).

2 block:

  • Monolith — 100%;
  • masonry — 100%;
  • ventilation — 95% (ventilation equipment is being installed);
  • sewerage, water supply — 95% (risers installed, intra-apartment wiring, installation of meters);
  • roofing device, the screed is 100% completed, the first layer of waterproofing was applied;
  • work is being done on the construction of transformer substations, installation of equipment, arrangement of premises;
  • facade: 80% of aluminum subsystems installed, 20% of sandwich panels, installation of double-glazed windows.

3 block:

  • Monolith — 100%;
  • masonry — 80%;
  • ventilation — 90%;
  • sewerage, water supply — 80% (installation of risers has begun);
  • facade: 5% of aluminum subsystems installed.

Work is being actively carried out on the arrangement of engineering networks of the parking lot, the technical premises of the parking lot are 70% completed, the equipment of pumping stations has been delivered.