Port City construction progress
We invite you to find out the dynamics of the construction of the Port City apart-complex.
1 block:
- Monolith — 100%;
- masonry — 100%;
- ventilation — 100%, (ventilation equipment at the final stage)
- sewerage, water supply — 100% (risers installed, intra-apartment wiring completed, meters installed);
- fire safety cables have been laid, fire cabinets are being formed;
- roofing device — 100%;
- work is being done on the construction of transformer substations, installation of equipment, arrangement of premises;
- installation of aluminum subsystems, balcony railings — 95%;
- Facade works are in full swing, installation with double-glazed windows, ceramics, sandwich panels — completed by 40%;
- facade lighting (power cable lines laid, the first lamps installed).
2 block:
- Monolith — 100%;
- masonry — 100%;
- ventilation — 95% (ventilation equipment is being installed);
- sewerage, water supply — 95% (risers installed, intra-apartment wiring, installation of meters);
- roofing device, the screed is 100% completed, the first layer of waterproofing was applied;
- work is being done on the construction of transformer substations, installation of equipment, arrangement of premises;
- facade: 80% of aluminum subsystems installed, 20% of sandwich panels, installation of double-glazed windows.
3 block:
- Monolith — 100%;
- masonry — 80%;
- ventilation — 90%;
- sewerage, water supply — 80% (installation of risers has begun);
- facade: 5% of aluminum subsystems installed.
Work is being actively carried out on the arrangement of engineering networks of the parking lot, the technical premises of the parking lot are 70% completed, the equipment of pumping stations has been delivered.